Montrose County approved Energy Fuels' Special Use Permit on September 30, 2009. Energy Fuels subsequently submitted the Material License Application and Environmental Report to the State of Colorado on November 18, 2009.

 

On January 5, 2011, the State of Colorado issued a Radioactive Materials License to Energy Fuels. While there are other permits needed before construction can begin, the Radioactive Materials License is the primary permit needed to build and operate the Piñon Ridge Mill. Construction on the mill is anticipated to begin in late 2011 or early 2012.